Another project complete!
This is a project which we carried out for Flavour Base in Bolsover – we have been doing work for them for over 20 years and they are a valued customer of ours the project included –
- plastic cladding of walls where damaged – form the bends with a bespoke plastic bender
- movement of existing wall and reinstate in new position to make room for a new mixer to be installed
- install new 3 phase electrical supply for the new mixer
- install new 5 foot NCF light fittings
- re position existing electrical sockets
- support the ceiling with drop rods and unistrut fixings
- installed new flooring where damaged to make the floor completely water tight
- bespoke stainless steel capping to all exposed edges
This all took 4 – 5 days to complete and was co ordinated with the customer to minimise disruption
The job was signed off by the on site manager Paul who was extremely happy with the final product
If you have any enquires for any similar works please contact the office on 01623740047 or email info@brodalecatering.co.uk
Thanks for looking!